AsstrA Overcomes Chittagong Challenges for US Delivery


642-Ton Power Generation Package Successfully Shipped to Port of Houston



By Simon West

AsstrA-Associated Traffic pulled out all the stops to deliver a complex shipment of project cargo from Bangladesh to the U.S.

A main power generation package comprising generators and associated equipment weighing 642 tons was loaded at the Port of Chittagong in March and arrived at the Port of Houston in June. The 40 individual packages had a volume of 3,557 cbm.

A key challenge for the project team was managing the part-charter operation with a fixed laycan window for loading at Chittagong. The cargo was transferred by four barges from the point of rest in Bangladesh to the port with a one-day transit time. Despite the slow, safety-focused transfer from barge to ship, the operation was completed smoothly and within the 48-hour window, Zurich-headquartered AsstrA said.

Among other hurdles was the export customs clearance process in Chittagong, which required extensive coordination between multiple stakeholders.

“The operation and maneuvers in Chittagong from barge to ship proved challenging, but being there to support and assist in the process reduced risks and delays,” said Colin Bagwell, team leader of IPL North America Division at AsstrA.

“Furthermore there were a number of parties involved so the coordination and management time was ultimately essential and time well spent. Avoidance of delays and additional cost was also a challenge, but all overcome through close management, partnerships with customer and service providers plus open and clear communication, but above all else detailed planning.”

The project, which began with an initial planning phase in 2023, demonstrated AsstrA’s ability to manage high-stakes transport challenges, the company added.

AsstrA is an exhibitor at Breakbulk Europe.

Back