3,700-Tonne Structure Transported and Lifted in One Piece in Under 24 Hours

By Simon West
Mammoet has transported and installed a new 3,700-tonne bridge in one piece in Hamburg, with the operation completed in less than 24 hours to minimize disruption to the city’s transport network.
Mammoet, an expert in Accelerated Bridge Construction (ABC), worked with project owner Deutsche Bahn and general contractor SHE Engineering to move the fully assembled Sternbrücke Bridge into position, using self-propelled modular transporters (SPMTs) and specialist lifting equipment.
The operation involved 272 axle lines across two SPMT configurations and 16 climbing jacks, each with a 500-tonne capacity. The bridge was transported some 500 meters along Max-Brauer-Allee before being rotated 45 degrees and lowered into its final position.
The project presented significant logistical challenges, with just 30cm of clearance between the bridge and surrounding buildings at the narrowest points. A just-in-time delivery strategy was also required to accommodate the limited assembly and equipment mobilization space in the densely built-up urban area.
“This was our biggest challenge: the logistics and organization of our equipment inside a very small area,” said Lars de Haas, project manager at Mammoet. “Had we set up our trailers beside the bridge, it would have taken up all the space available and meant we wouldn’t have a laydown area. Anything arriving would immediately have to be assembled. There was a lot of work to ensure everything arrived just in time and in the correct order”.
Mammoet first conducted a feasibility study in 2017, with detailed planning supported by 3D site scans and engineering simulations to establish the transport route and equipment requirements.
The replacement was necessary because the original Sternbrücke had reached the end of its service life and could not feasibly be renovated. The railway bridge carries around 1,000 long-distance, regional and commuter trains daily, while the roads beneath it serve tens of thousands of vehicles.
“I’ve been working for Mammoet now for over 15 years and this is one of the highlights of my career,” said Jamie Groeneweg, lead engineer at Mammoet. “It might not be the heaviest, nor the largest bridge we’ve moved, but it certainly had a big impact. So yes, for me, it was a special moment.”
Mammoet will be exhibiting at Breakbulk Europe 2027.